[{"createTime":1735734952000,"id":1,"img":"hwy_ms_500_252.jpeg","link":"https://activity.huaweicloud.com/cps.html?fromacct=261f35b6-af54-4511-a2ca-910fa15905d1&utm_source=V1g3MDY4NTY=&utm_medium=cps&utm_campaign=201905","name":"华为云秒杀","status":9,"txt":"华为云38元秒杀","type":1,"updateTime":1735747411000,"userId":3},{"createTime":1736173885000,"id":2,"img":"txy_480_300.png","link":"https://cloud.tencent.com/act/cps/redirect?redirect=1077&cps_key=edb15096bfff75effaaa8c8bb66138bd&from=console","name":"腾讯云秒杀","status":9,"txt":"腾讯云限量秒杀","type":1,"updateTime":1736173885000,"userId":3},{"createTime":1736177492000,"id":3,"img":"aly_251_140.png","link":"https://www.aliyun.com/minisite/goods?userCode=pwp8kmv3","memo":"","name":"阿里云","status":9,"txt":"阿里云2折起","type":1,"updateTime":1736177492000,"userId":3},{"createTime":1735660800000,"id":4,"img":"vultr_560_300.png","link":"https://www.vultr.com/?ref=9603742-8H","name":"Vultr","status":9,"txt":"Vultr送$100","type":1,"updateTime":1735660800000,"userId":3},{"createTime":1735660800000,"id":5,"img":"jdy_663_320.jpg","link":"https://3.cn/2ay1-e5t","name":"京东云","status":9,"txt":"京东云特惠专区","type":1,"updateTime":1735660800000,"userId":3},{"createTime":1735660800000,"id":6,"img":"new_ads.png","link":"https://www.iodraw.com/ads","name":"发布广告","status":9,"txt":"发布广告","type":1,"updateTime":1735660800000,"userId":3},{"createTime":1735660800000,"id":7,"img":"yun_910_50.png","link":"https://activity.huaweicloud.com/discount_area_v5/index.html?fromacct=261f35b6-af54-4511-a2ca-910fa15905d1&utm_source=aXhpYW95YW5nOA===&utm_medium=cps&utm_campaign=201905","name":"底部","status":9,"txt":"高性能云服务器2折起","type":2,"updateTime":1735660800000,"userId":3}]
来自国铁集团的官方消息,1 月 20 日,经过 13 年的艰苦建设,大瑞铁路(大理至瑞丽)秀岭隧道平导顺利贯通,单口掘进长度达 9677
米,刷新了亚洲铁路山岭隧道独头掘进的最长纪录。
大瑞铁路大保段(大理至保山)桥隧比例达 86.5%,共有隧道 21 座,目前已贯通 18 座。
其中,秀岭隧道位于云南省大理白族自治州漾濞县境内,全长 17.623 公里,属于特长隧道,工期长达 13 年。
(图自@中国铁路)
目前国内在进行特长隧道施工时,大多数是采用设置横洞、斜井、竖井等施工方法,以增加隧道开挖工作面,从而达到“长隧短打”的目的。
但是,秀岭隧道环境特殊,只能采取进出口两端长距离掘进的方式,导致施工难度大、进度慢,也是影响大瑞铁路全线贯通的一个“超级拦路虎”。
同时,随着隧道掘进长度的不断延伸,洞内温度居高不下,掌子面最高超过 40℃,空气湿度更是接近 100%,施工单位不得不每天运送 10 多吨冰块到施工现场。
另外,秀岭隧道最大的埋深接近 1100 米,还有滇西红层软质岩的特殊性,施工中经常会遇到突泥涌水、软岩大变形、掌子面溜坍的风险,而且整条隧道要穿过 7
条断层破碎带,围岩每一米都在变化,施工难度可想而知。
为攻克秀岭隧道建设难关,云桂铁路(沪昆铁路客运专线)云南公司大瑞铁路指挥部组织参建各方,开展了 100 余项课题研究,获得国家专利 2
项、省部级科研成果 3 项、企业级科研成果 41 项。
大瑞铁路是我国《中长期铁路网规划》中完善路网布局和西部大开发重要项目,是中国与缅甸等中南半岛国家互联互通、通往印度洋的陆路运输大能力通道,投资
257.3 亿元,全长 330 公里,设计时速 140 公里,设计运输能力为客车 12 对/日,货运 1200 万吨/年。
大理至保山段预计 2021 年 12 月 31 日通车,保山至瑞丽段预计 2022 年 12
月通车,届时将结束云南保山、德宏等少数民族聚居区不通火车的历史,同时从大理至瑞丽将由目前公路运输的六七个小时缩短至 2 个多小时,从昆明至瑞丽仅需 4
个半小时左右。